What is the difference between overbilling and underbilling on a WIP schedule?
Overbilling and underbilling describe the gap between how much work you’ve completed on a project and how much you’ve billed the client. They show up on a Work in Progress schedule as opposite line items, and they affect your balance sheet in different ways.
Overbilling happens when your billings exceed the costs you’ve incurred relative to total estimated project costs. If a project is 40% complete based on costs but you’ve billed 60% of the contract, the difference is overbilling. This shows up as a liability on your balance sheet because you’ve collected money for work you haven’t performed yet. You owe that work to the client. The formal term you’ll see on financial statements is “billings in excess of costs and estimated earnings.”
Underbilling is the opposite. You’ve completed more work than you’ve billed for. If a project is 60% complete but you’ve only billed 40%, that gap is underbilling. This shows as a current asset because you’ve earned revenue that you haven’t collected yet. The formal term is “costs and estimated earnings in excess of billings.” You have a right to bill for that work and you should be collecting it.
A simple example helps. Say you have a $500,000 contract with estimated costs of $400,000. You’ve spent $200,000 so far, which means the project is 50% complete. At 50% completion, you’ve earned $250,000 in revenue. If you’ve billed $300,000, you’re overbilled by $50,000. If you’ve only billed $200,000, you’re underbilled by $50,000.
Neither overbilling nor underbilling is automatically bad, but patterns matter. Consistent overbilling across all projects means you’re front-loading cash collection, which helps cash flow but creates a large liability position. Consistent underbilling means you’re financing the client’s project with your own money, which strains cash flow and can signal billing process problems. Bonding companies and lenders look at both carefully because the pattern tells them how well you manage projects and cash.
The WIP schedule has to be tracked per project, not in aggregate. A company might look balanced overall but have one project severely overbilled and another severely underbilled. Construction job costing that tracks labor, materials, and subcontractor costs by project is the foundation for producing an accurate WIP schedule. Without reliable cost tracking at the project level, your overbilling and underbilling numbers are meaningless.
Bonding companies use WIP schedules to evaluate whether you can handle additional bonding capacity. Lenders use them to assess the real financial health of your company beyond what the income statement shows. If your WIP schedule is inaccurate or you can’t produce one, it raises red flags that can cost you bonding capacity or loan approval.
Keeping your WIP schedule current requires updating cost estimates regularly. The original estimate rarely holds perfectly, and failing to revise it means your percent-complete calculation drifts from reality. A project where costs have overrun the original estimate will show misleading overbilling or underbilling numbers until you update the total estimated cost. This is where many contractors get tripped up. They set the estimate at the beginning and never revisit it.
If you’re a contractor in the Phoenix area working with bonded projects or pursuing larger contracts, having bookkeeping services that understand WIP reporting is not optional. Accurate WIP schedules are how you prove financial health to the people who decide whether you get the next bond or the next line of credit.
Your Valley of the Sun Bookkeeper
The Next Step:
A Quick Conversation
Tell us what's going on with your books. We'll listen, ask a few questions, and give you a clear quote with no surprises.
More Questions
How do I reconcile my construction project budget against actual costs at month end?
Pull a job cost report showing budget versus actual by cost code for every active project. Calculate line-item variances, add committed costs from open POs and subcontracts, and update your cost-to-complete estimates. This monthly process feeds your WIP schedule and shows which jobs are really making money.
Read answerHow should I account for security deposits received and returned on rental properties?
Security deposits are a liability, not income. Record them to a liability account when received and reverse the entry when returned. If you retain any portion for damages, reclassify that amount to income and record the repair expense separately.
Read answerHow much should an owner-operator set aside for quarterly estimated tax payments?
Set aside 25 to 30 percent of your net income after expenses. That range covers federal income tax, self-employment tax, and Arizona state tax. Transfer the money weekly into a separate savings account so it's ready when quarterly payments come due.
Read answerWhat are the most commonly missed tax deductions for owner-operator truck drivers?
Per diem alone can save owner-operators thousands each year, and most drivers miss it entirely. Other commonly overlooked deductions include ELD device fees, lumper fees, scale tickets, truck washes, and DOT physicals.
Read answerCan I deduct hand tools and power tools as a self-employed electrician or do I depreciate them?
Most hand tools and power tools under $2,500 can be deducted immediately using the IRS de minimis safe harbor election. Tools over $2,500 can be fully deducted through Section 179 or depreciated over 5 to 7 years. Either way, keep every receipt because tool deductions are a common audit flag for trades.
Read answerHow should a real estate brokerage track individual agent commissions and 1099 reporting?
Set up QuickBooks Online with classes or sub-customers for each agent. Track gross commission received, agent split paid, and brokerage retention per transaction, then use those records to generate 1099-NECs at year end.
Read answer